Power System Studies

Power system studies are conducted to cover key principal design aspects of a power distribution network. These are classified into

Load Flow Studies
Load-flow studies are performed to determine the steady-state operation of an electric power system. The studies cover aspects such as voltage gradient across downstream equipments, the voltage profile at each bus system, power trends in all branch and feeder circuits. Total system losses contributed by individual system components are also calculated.
Load-flow studies determine if system voltages remain within specified limits under various loading conditions, and if transformers, generators, cables and switchgear are overloaded. Load-flow studies identify the need for additional installed capacity, assess redundancy, capacitive, or inductive VAR support to maintain system voltages within specified limits.

Top


Short Circuit Studies
Short-circuit studies are performed to determine amplitude of currents that flow in a power system during electrical faults. Faults may occur at any location within a power network and fault currents contributed by each such location; namely utility service entrance, transformers & generators, UPS, Motors, cables, etc are estimated.
Before upgrade of installed capacity of, say a transformer, existing & projected fault levels must be verified in order to assess suitability of breaking capacities of switchgear, cable, etc. Since occurrence of a fault results in associated drop in voltage of the fault zone, effect on associated equipments is also estimated.
Short circuit studies calculate network impedances and form basis for protection co-ordination studies. Effect of paralleling and synchronizing are also considered from view of increased fauld levels.

Top


Protection co-ordination
Protection co-ordination studies are performed to ensure faster clearance of faults and avoidance of nuisance tripping of feeders for faults occurring out of their respective zone; thus allowing neighboring equipments to perform without interruption. Protective relaying requires periodic calibration, servicing, testing and upgrade, which is also reviewed.
Although common protections are against overload, short circuit and earth fault each equipment may require different scheme of protection. Transformers, generators, motors, cables, bus bars, switchgear are provided with distinct protection schemes and yet these must be co-ordinated with up stream protection schemes so that faults are limited to their location and upstream protection works as back up if downstream protection fails or delays in operation.
Protection co-ordination studies also review various requirements such as inrush currents of transformer, motor, capacitor, nominal and full load conditions of plant, pre-load and ambient temp compensation for fuse, hot & clod load pick up, auto re-closing schemes, motor staring & locked rotor curves, etc. Characteristic curves such as thermo-mechanical damages to transformers & alternators, motors, cables, switchgear, etc are generated & plotted against performance characteristics curves for verifying time/current setting of protective relaying.
IEEE 242-2001 standards referring to Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems may be followed in certain cases.

Top


Insulation co-ordination
Insulation co-ordination studies are generally covered during principal design of plant and may continue to be valid provided no changes take place for a few years. Insulation review becomes essential when one of more of conditions take place, namely sudden rise in frequency of faults, frequent equipment failures, rise of utility voltage levels, upgrade of utility of customer's installed capacity, installation of new type of load, i.e. a number of LV motor of large size with star-delta start are replaced with that of VFDs or HV motors are replace with VFDs.
Similarly, process plant with established corrosion & air contamination levels exhibit rapid deterioration of insulation properties. Installation with dissimilar insulation material for identical voltage levels may find frequent failures that call for co-ordination studies.
Insulation co-ordination studies are conducted at all voltage levels existing in a plant. Upstream equipments such as lightening arrestors, and distribution schemes incorporating Transient Voltage suppressers, Surge arrestors in VCBs are also reviewed.

Top

ARC Flash Hazard

Electrical arcs resemble deadly weapons stored within an electrical installation and could prove extremely hazardous to human life and property. Electric arc could lead to explosion with release of very high energy, could result in serious injury or sudden death, electrical fires and other consequent damages.

All switching equipments undergo arcing during normal operation and are designed to withstand and quench the arc on continuous basis. However, under abnormal conditions like short circuits, fault energy may initiate an arc that could not be controlled by the switchgear, may propagate and escape to outside; injuring an unprotected working personnel nearby.

Arc flash hazard analysis is conducted with following objectives

1. To calculate fault energy at key locations within a power distribution network.
2. To establish arc flash boundaries at these locations.
3. To recommend appropriate protective gear for operating personnel.
4. To design warning labels to be installed at such locations.

Personnel working in the vicinity of electrical equipments such as High & Low Voltage Switchboards, Outdoor switchyards, Transformers, Large Motors are under constant threat of arc flash hazards and must therefore be trained in protective measures.

A typical arc flash hazard program comprises of

1. Field survey and power system studies reviewing protective relaying, equipment aging, insulation levels and thermal imaging.
2. Establishment of arc flash energy levels, risk levels and protective boundaries at various locations generally referred to IEEE 1584.
3. Generation of warning labels and brief training program.
4. Selection of appropriate protective gear at these levels.

When to perform arc flash hazard studies
When one or more of conditions listed below apply to an installation, it is recommended to get the study conducted
1. Change in Electric Utility Installation including upgrade of installed capacity, change in voltage level, etc.
2. Protective relaying is not calibrated / tested for a few years.
3. Recent fault occurrence.
4. Addition of transformers or motors within an installation.
5. Facility not supported with appropriate O & M practices.

Critical Load / Disaster Management
Critical load may be defined as that set of primary equipments that support the process of the business and shutdown of which would result in substantial losses.
Critical load management applications are found in all major business; airport, shipping, logistics, continuous process plants, server farms & data centers, ATMs, hospitals, telecom installations, Cellular units, etc.
The basis of critical load management lies in identifying single point of failure in the electrical scheme and creating redundancy to compensate for should the failure occurs.
Energy Integra offers services that cover various aspects in critical load / disaster management.

  • Field survey, study of scheme and identification of critical load scheme.
  • Identification of single point of failure and devise means to create redundancy.
  • Formulation of solution, assistance for implementation.
  • Field testing to ensure of success of scheme.
  • Continued support.

Field testing comprises of review of existing scheme for reliable operation of raw power back up / auto changeover, UPS & static bypass, synchronization and load shedding, etc.

Existing scheme may undergo modification, extension or installation of additional equipments may be recommended to enhance reliability and redundancy.

O & M practices and inventory are reviewed and suggestions offered for improvement.

Top